Trenchless Solutions Limited was contracted to install a new section of pipeline using trenchless techniques at Musley Bank as part of Phase 2 of the works. The project required a high level of installation accuracy to accommodate the pipeline beneath challenging ground conditions and within a constrained working area.
The site presented a number of challenges, including restricted access, proximity to existing services, and environmental considerations, making open-cut excavation unviable. A trenchless approach using Horizontal Directional Drilling (HDD) was selected to minimise disruption and ensure precise alignment.
Working on behalf of the client, Trenchless Solutions Limited completed the installation using a controlled Horizontal Directional Drilling operation.
The works involved the completion of a pilot bore, followed by progressive reaming to achieve the required diameter, and the installation of the product pipe via pullback along the designed alignment.
All works were carried out within a confined working area, ensuring accuracy of line and level while maintaining minimal disruption to the surrounding environment.
| Proposed open cut construction | As built trenchless construction |
|---|---|
Restricted access:
|
Restricted access:
|
Health & safety:
|
Health & safety:
|
Cost savings:
|
Cost savings:
|
Environmental:
|
Environmental:
|