Project Overview
YW investigated a flooding event adjacent to a foul sewer. Further CCTV and investigation work
found that a DN300 VC foul water sewer pipeline was 100% full of concrete. The foul sewer was
then placed on mitigation until a solution was found.
A solution was presented to YW by an alternative contractor which required the replacement of
60m of DN300 VC at a depth of 3.5 metres by open cut installation. The proposed solution would
have required a full road closure in the city centre for a duration of 16 weeks. Leeds City Council
Highways department rejected the proposal.
Description of Works
Trenchless Solutions were appointed to undertake a trenchless installation, construct the shafts,
and provide attendances. The new section of pipeline was constructed using DN300 Naylor Denlok
NC vitrified clay jacking pipe, following installation the new pipeline was connected into the existing
foul sewer in the drive and reception shafts by a selection of bends and stub pipes.
Proposed 16 Week Open Cut Construction | As Built 5 Week Trenchless Construction | |
Restricted Access: • Leeds General Infirmary |
Restricted Access: • Leeds General Infirmary |
|
Health & Safety: • Risk from Existing Utilities |
Health & Safety: • Reduced Risk from Existing Utilities |
|
Cost Saving:
• Proposed 16 Week Duration of Project |
Cost Savings:
• As Built 5 Week Duration of Project |
|
Environmental: • CO2 Emissions (tonnes) as Built – 52.8 |
Environmental:
• CO2 Emissions (tonnes) as Built – 12.5 |