Guided Auger Boring – Installing DN225

Project Overview:

Flooding and a sink hole appeared within a Parish Council Recreational Playground. CCTV work was
carried out and a collapsed sewer was found to be at fault.

Description of Works:

YW appointed TSL to dig and repair the collapsed sewer, as the repair was made further collapses
appeared along the sewer pipeline. Trenchless Solutions carried out further investigation and due
to the ground conditions being running sand, with a high-water table and environmental issues
with mature tree canopies above the existing pipeline, TSL proposed an off line replacement of
DN225 Denlok VC foul sewer by GAB.


 

 

Proposed Open Cut Construction  As Built Trenchless Construction

Restricted Access:

• 5 No. Mature Trees
• High Water Table
• Running Sand

Restricted Access:

• No Removal of Mature Trees Required
• No Effect by the High Water Table
• No Effect by Running Sand

Health & Safety:

• Temporary Deep Trenches
• Increased Temporary Works

Health & Safety:

• No Temporary Deep Trenches
• Reduced Temporary Works

Cost Saving:

• Increased De-Watering
• Increased Time of Over-Pumping
• Increased Duration of Project
• Material Reinstatement Costs, Tipping / Inert

Cost Savings:

• De-Watering only required around shafts
• Reduced Time of Over-Pumping
• Reduced Duration of Project
• Reduced Material Reinstatement Costs

Environmental:

• CO2 Emissions (tonnes) as Built – 16.8
• Noise

Environmental:

• CO2 Emissions (tonnes) as Built – 14.1
• Reduced Noise