The Naylor Denlok DN225 clay drainage pipe has been jacked in at Louth to the complete the project. The site will now be cleared and all thrust boring equipment returned to Barnsley to complete the project in good time.
The mts Perforator PBA85V guided thrust boring system (pull back technique) was used to install 700m of gravity sewer in Scarborough. 180mm SDR11 black PE pipe was installed to "straight" accurate line and gradient in various drive lengths betweeen 55 to 65 metres.
Take a look at our project video of our recently completed Guided Auger Boring works. A total of 36 metres of DN600 Concrete Pipe was installed to accurate line & grade.