Another project starting today with equipment delivered to site this morning to install 3 crossings of DN150 Naylor Industries PLC Denlok clay jacking pipe using our mts Perforator PBA85 system.
The mts Perforator PBA85V guided thrust boring system (pull back technique) was used to install 700m of gravity sewer in Scarborough. 180mm SDR11 black PE pipe was installed to "straight" accurate line and gradient in various drive lengths betweeen 55 to 65 metres.
Take a look at our project video of our recently completed Guided Auger Boring works. A total of 36 metres of DN600 Concrete Pipe was installed to accurate line & grade.