Busy, Busy Times Ahead for TSL

Our project in Derby is now complete. A total of 67m of Naylor Denlok DN225 clay jacking pipe installed to accurate line, level and grade, split into two seperate drives.

We have two projects starting soon in Nottingham. One project involves the a 19m crossing of 324mm o/d lost steel casings which will be used for cable ducting underneath the new Nottingham super tram. Then following on we have a project involving the installation of 30m Naylor Denlok DN225 clay jacking pipe which will be used for drainage under the new super tram also.

Also equipment is being mobilised for a UTX project involving a 20m crossing of 457mm o/d lost steel casings.

Keep checking back for more updates on these and future projects.