On Friday Trenchless Group held a charity golf day for Candlelighters Trust & Combat Stress: The Veterans’ Mental Health Charity. Two fantastic charities who have made a massive difference to their users…
So far we have tallied up that in excess of £8,800 has been raised but there’s still more to come!!!
Thank you to everyone who attended and made the day so great!!!
The mts Perforator PBA85V guided thrust boring system (pull back technique) was used to install 700m of gravity sewer in Scarborough. 180mm SDR11 black PE pipe was installed to "straight" accurate line and gradient in various drive lengths betweeen 55 to 65 metres.
Take a look at our project video of our recently completed Guided Auger Boring works. A total of 36 metres of DN600 Concrete Pipe was installed to accurate line & grade.