TSL were asked to install 2 number short crossings into Armley road. The client had planned to use open cut methods but found various services running up the footpath and a main gas supply in the road. Using our mts Perforator PBA85 guided auger boring machine it took a total of 3 days to install both the 400mm foul and the 300mm surface Naylor clay drainage pipes. Well done Mark B, Jamie and Mick!!