Great work lads !! Piloting successfully completed, installed to perfect line and grade.
Here at Trenchless we can help with your next project undertaking full contract work or utilising your own workforce and rent our systems c/w operator.
See our detailed 3D animation of the trenchless method
The mts Perforator PBA85V guided thrust boring system (pull back technique) was used to install 700m of gravity sewer in Scarborough. 180mm SDR11 black PE pipe was installed to "straight" accurate line and gradient in various drive lengths betweeen 55 to 65 metres.
Take a look at our project video of our recently completed Guided Auger Boring works. A total of 36 metres of DN600 Concrete Pipe was installed to accurate line & grade.