6 Number drives successfully completed at Nottingham
News
14th October 2014
6 Number drives successfully completed at Nottingham
6 Number drives successfully completed at Nottingham so far, 3 drives to go pictures of the 600mm #Hobas GRP jacking being installed to very accurate line and grade “well done Mark, Oliver and Jamie”
The mts Perforator PBA85V guided thrust boring system (pull back technique) was used to install 700m of gravity sewer in Scarborough. 180mm SDR11 black PE pipe was installed to "straight" accurate line and gradient in various drive lengths betweeen 55 to 65 metres.
Take a look at our project video of our recently completed Guided Auger Boring works. A total of 36 metres of DN600 Concrete Pipe was installed to accurate line & grade.