45m Pilot bore completed to line and level today in Rossendale, Lancs. Working out of a 6m deep 2.4m Shaft going to a sheeted cofferdam. The new DN225 #Naylor #Denlok Clay Jacking product pipe will be tied into an existing channel / manhole base which will be reconstructed upon completion of our works.
Well done Jamie and Tom on an accurate pilot, which had no room for error. Good Job.